FRONT WALL INSTALLATION
Remove temporary wall support.
Center front wall assembly between the side walls.
BEGIN
1
2
Secure front wall to side walls using one 2" screw into
top and bottom plates (Fig. A).
2" (5,1 cm)
x4
2" (5,1 cm)
x4
PARTS REQUIRED:
ENSURE TOP OF WALL FRAMES ARE FLUSH.
3
Nail lower edge of front wall panels to oor using 2" nails 6" apart. Angle nail to hit oor frame (Fig. B).
ENSURE FRONT AND SIDE WALL PANELS ARE FLUSH BEFORE SECURING.
6"
(15,2 cm)
Flush
Flush
Fig. B
Angle nail to hit

Flush
Flush
2" (5,1 cm)
Screw
2" (5,1 cm)
Screw
2" (5,1 cm)
Screw
2" (5,1 cm)
Screw
2" (3,8 cm)
Screw
Flush
Fig. A
2" (5,1 cm)
Nail