Installation Guide

59
12' GABLE WALL 01 WITH DOOR INSTALLATION
3" (7,6 cm)
x2
3" (7,6 cm)
x8
2
Place 12' gable wall on  oor, centered
between installed walls.
Secure wall with 2" screws into top and bottom plates
(Fig. A, Fig. B).
Secure wall to bottom plate fi rst.
BEGIN
1
Nail lower edge of panels to  oor
with 2" nails spaced 6" apart.
Angle nails into  oor frame (Fig. C).
Nail panels to 24' wall studs with
1-1/2" nails spaced 6" apart.
ENSURE PANEL CORNERS ARE FLUSH.
Your walls are now installed.
FINISH
CUT OUT AND REMOVE BOTTOM PLATE
AT DOOR OPENING.
REMOVE TEMPORARY BRACING.
2" (5,1 cm)
x16
1-1/2" (3,8 cm)
x26
2" (5,1 cm)
x4
PARTS REQUIRED
Secure wall top plates with 3" screws
at each corner at an angle (Fig. D).
3
STANDARD:
DOOR LOCATED
ON 12' GABLE WALL
2" (5,1 cm)
Nails
1-1/2"
(3,8 cm)
Nails
6" (15,2 cm)
6"
(15,2 cm)
3" (7,6 cm)
Screw
Fig. D
3" (7,6 cm)
Nails
Nail 2" nails  rst.
2" (5,1 cm)
Nails
Fig. C
3" (7,6 cm)
Nails
2" (5,1 cm)
Screw
Flush
Flush
2" (5,1 cm)
Screw
Fig. A