69
PARTS REQUIRED:
2nd 20' EAVE WALL 12 INSTALLATION
Secure wall with (1) 2" screw through
gable wall panel into 12' wall bottom
and top plates (Fig. A, Fig. B).
Secure wall to bottom plate fi rst.
ENSURE PANEL CORNERS ARE FLUSH.
BEGIN
1
2
2" (5,1 cm)
x2
Flush
2" (5,1 cm)
Screw
Fig. B
Place 2nd 20' wall 12 centered on oor.
1-1/2" (3,8 cm) overlap is to the top.
Use TJ as a temporary brace as shown.
Secure TJ with (2) 3" screws.
TJ
3" (7,6 cm)
Screws
3" (7,6 cm)
x2
x1
2 x 4 x 92-5/8" (5,1 x 10,2 x 235 cm)
TJ
Temporary Brace
1-1/2"
(3,8 cm)
3" (7,6 cm)
x20
2" (5,1 cm)
x45
Nail 2" nails rst.
2" (5,1 cm)
Nails
Fig. C
3" (7,6 cm)
Nails
3" (7,6 cm)
Nails
3
Nail lower edge of wall panels to oor
frame with 2" nails spaced 6" apart.
Angle nails into oor frame (Fig. C).
Secure wall bottom plates to oor
with 3" nails (Fig. C).
6"
(15,2 cm)
2" (5,1 cm)
Screw