12x8 Metropolitan Instructions

7
DOOR
FLOOR LEVELING OPTIONS
There are multiple ways to level your oor frame. Our recommended leveling method is shown below.
Leveling materials are not included in this kit.
PREFERRED METHOD - 4x4 TREATED RUNNERS
Measurements to
centerof4x4's.
• 3" Screws angled into 4x4.
• (2) at each point frame
and 4x4 touch.
• Level under 4x4 runners only.
• Locate leveling material 12" from ends of runners and no more than 48" apart.
Asphalt shingles should be used between 4x4 runners and blocks or treated lumber. Never use
shingles in direct contact with ground.
• For best results and aiding in water drainage use gravel under each concrete block.
LEVELINGMETHODS
If you are building your shed on a concrete foundation see the following page.
CONCRETE
MATERIALREQUIRED
x2
4" x 4" x 12' (10 x 10 x 365,8 cm)Treated Lumber
FastenersforFrameto4"x4".
(3" Screws shown as one option.) Minimum (40) 3" screws / exterior grade.
Useonlywoodtreatedforgroundcontactandfastenersapprovedforusewithtreatedwood.
Alwayssupportframeseams.
Levelinghigherthan16"notrecommended.
LEVELINGMATERIALS
Gravel
2x4 Treated Lumber
Solid Masonry Blocks in 1", 2", 4" or 8" thickness
Asphalt Shingles
8" Block
4" Block
Gravel
Gravel
Do not exceed 16".
4x4 Runner
Shingle
Shingle
Maximum between leveling
material locations.
48"
12"
2x4 Treated Lumber
2" Block
Level
12"
12"
(30,5 cm)
12"
(30,5 cm)