All cables (power and signal) should pass through the screw-in metal cable glands provided. The
screen of the power cable should be terminated at the cable gland.
Power cables need to be fitted with a ferrite ring inside the detector case (2 off provided). The 24V
and 0V wires should be long enough to form a loop around the ferrite wall.
Separate wires from the power cables should be kept as short as possible, just enough to provide
adequate stress relief.
Diagrams below show the appropriate arrangements for top and rear entry cables: