9 Commissioning 
Local standards and specification requirements must be adhered to. A typical commissioning procedure 
might entail the following steps: 
Check installation against 
design documentation
T 
Set detector configuration DIL 
switches as required 
T 
Disconnect detector from fire 
panel if required 
T 
Power up detector and wait for 
15 minute FastLearn cycle to 
finish (steady “OK” LED when 
complete) 
T 
Check/test connections to main 
Fire Detection and Alarm 
System 
T 
Smoke test: check maximum 
transport time is less than 120s, 
verify sampling hole sensitivities 
as required. Verify that smoke is 
not prevented from reaching 
sampling holes, e.g. by strong 
air currents such as might be 
caused by air-conditioning  units
T 
Reconnect detector to fire panel 
if
 required 
T 
Complete test records; record 
settings and results for 
reference by maintenance 
engineers 