REDUCE INSTALLATION COSTS WITH THE
HOLDRITE® HYDROFLAME™ PRO SERIES
Application Cost Savings Analysis Example
Install sleeve and firestop for a 2” pipe through an 8” thick concrete slab on a wood form deck.
HOLDRITE HydroFlame PRO SERIES™
Installation Steps
Approx.
Mat. Cost
Labor
Time
1. Select sleeve size and nail it
to form deck
(concrete poured by others)
$9.00 2 minutes
2. Remove cap and install pipe
with riser clamp
2 minutes
TOTALS:
Approximate Material Costs $9.00
Time 4 minutes
Labor Cost at $50/hour $3.33
Total Installed Cost
(T&M)
$12.33
Problematic Plastic Concrete Sleeve
Makeshift Method
Installation Steps
Approx.
Mat. Cost
Labor
Time
1. Select 4” sleeve, measure
and mark for saw cutting
$3.00 1 minute
2. Cut sleeve, in prep for
re-assembly to slab height
of 8”
1 minute
3. Build sleeve to height with
screw gun, screws and tape
50
¢
3 minutes
4. Nail sleeve to form deck
(concrete poured by others)
2 minutes
5. Remove/demolish sleeve out
of hole
5 minutes
6. Buy material, cut, build and
install hole cover (OSHA)
$1.00 2 minutes
7. Clean-up sleeve debris on
floor below
1 minute
8. Remove hole cover. Install
pipe with riser clamp
2 minutes
9. Collect, store and re-
distribute hole cover upstairs
1 minute
10. Remove riser clamp for
access to annular space
1 minute
11. Install and compact mineral
wool material into annular
space
50
¢
2 minutes
12. Install fire caulk to proper
thickness and trowel level
$1.00
2 minutes
13. Re-install riser clamp (and
hope pipe didn’t settle)
1 minute
14. Clean debris, hands and
tools and caulking tube and
store for re-use
2 minutes
TOTALS:
Approximate Material Costs
$6.00
Time 26 minutes
Labor Cost at $50/hour
$21.67
Total Installed Cost
(T&M)
$27.67
“The HydroFlame Pro Series is a counter intuitive UL
Listed firestop device that reduces costs and provides a
higher quality engineered firestop solution that protects
the project against fire, smoke, gas and water damage.
Typically enjoyed cost savings on a hospital or hotel project
range from $25,000 to $75,000. Ultimately, the HOLDRITE
HydroFlame Pro Series protects the interest of the property
owner and exceeds building codes designed to safeguard
the general public.
Jim LeStage,
HOLDRITE/Specifications Manager
Save $15.34
per installation
over the problematic
makeshift method.