HOME-FLEX CSST 49
Steel Pipe Capacity Chart
Table 7.11 Natural Gas (½ PSI or less with 0.5 in w.c. drop)
Maximum Capacity of Schedule 40 Metallic Pipe in BTU/h (British Thermal Units per Hour) of Natural Gas by
Length of Piping Run
(Approximate 1,000 BTU/h Natural Gas per 1 CFH; based on a 0.6 specic gravity of gas)
Maximum Gas Pressure:
½ PSI Pressure Drop: 0.5 in w.c.
Run
(ft.)
Metallic Schedule 40 IPS Pipe Size
¼" ⁄" ½" ¾" 1" 1¼" 1½" 2" 2½" 3" 4"
10 43k 95k 175k 360k 680k 1,400k 2,100k 3,950k 6,300k 11,000k 23,000k
20 29k 65k 120k 250k 465k 950k 1,460k 2,750k 4,350k 7,700k 15,800k
30 24k 52k 97k 200k 375k 770k 1,180k 2,200k 3,520k 6,250k 12,800k
40 20k 45k 82k 170k 320k 660k 990k 1,900k 3,000k 5,300k 10,900k
50 18k 40k 73k 151k 285k 580k 900k 1,680k 2,650k 4,750k 9,700k
60 16k 36k 66k 138k 260k 530k 810k 1,520k 2,400k 4,300k 8,800k
70 15k 33k 61k 125k 240k 490k 750k 1,400k 2,250k 3,900k 8,100k
80 14k 31k 57k 118k 220k 460k 690k 1,300k 2,050k 3,700k 7,500k
90 13k 29k 53k 110k 205k 430k 650k 1,220k 1,950k 3,450k 7,200k
100 12k 27k 50k 103k 195k 400k 620k 1,150k 1,850k 3,250k 6,700k
125 11k 24k 44k 93k 175k 360k 550k 1,020k 1,650k 2,950k 6,000k
150 10k 22k 40k 84k 160k 325k 500k 950k 1,500k 2,650k 5,500k
175 9k 20k 37k 77k 145k 300k 460k 850k 1,370k 2,450k 5,000k
200 8k 19k 35k 72k 135k 280k 430k 800k 1,280k 2,280k 4,600k
k = 1,000 BTU/h EXAMPLE: 10k = 10,000 BTU/h = 10 CFH (Cubic Feet per Hour) of Natural Gas