Installing a PTM
49HP StorageWorks ESL9000 Series Pass-Through Mechanism (PTM) Installation Guide
Installing the PTM assembly
To install the PTM assembly:
1. Remove the cable hole plug as shown in Figure 21 and install the grommet
provided into the hole.
Note: Two sizes of grommets were provided with the upgrade kit: 1.5 inch (0605061)
and 2 inch (0605060). Use the grommet that best fits the cable hole.
2. Reach through the hole (see Figure 21) and pull the pass through cable
through the hole, leaving approximately 18 in. of the cable on the front side of
the bin wall.
Figure 21: Cable hole location (ESL9326 shown)
(View from rear of library)
(View from front of library)
Cable hole
PTM Cable
Grommet