HP 1405 Switches Installation and Getting Started Guide (J9791A, J9792A, J9793A, J9794A)

2-5
Installing the Switch
Installation Procedures
1. Prepare the Installation Site
Cabling Infrastructure - Ensure the cabling infrastructure meets the
necessary network specifications. See appendix A, “Cabling and
Technology Information Specifications” for more information:
Installation Location - Before installing the switch, plan its location and
orientation relative to other devices and equipment:
On the back of the switch, leave at least 7.6 cm (3 inches) of space for
the twisted-pair cabling.
On the back of the switch, leave at least 3.8 cm (1 1/2 inches) of space
for the power cord.
On the sides of the switch, leave at least 7.6 cm (3 inches) for cooling.