HP StorageWorks XP Cluster Extension Software Administrator Guide (T1656-96035, April 2010)

For the journal fence level, you can update the Journal data currency on S-VOL and ASYNC
takeover timeout values. See JournalDataCurrency on page 136 and AsyncTakeover-
Timeout on page 130 for more information about these values.
4. Update the settings as needed, and then click OK to close the window.
5. Click OK to save your changes and close the window.
Notes
After a device group is configured in the resource configuration utility, do not change the device
group name or swap the name with another device group name in the HORCM file. If you do this,
restart the HORCM manager instance and reconfigure the XP Cluster Extension resource.
Do not use HORCM commands to change the device group property for a device group that is
configured for an XP Cluster Extension resource. If you do this, the changed property is not reflected
immediately in the Parameters tab. To work around this situation, re-select the device group from
the XP RM device group menu in the Parameters tab.
Configuring server data center assignments
1. Open Cluster Administrator and double-click the resource you want to edit.
2. Click the Parameters tab.
3. To remove a data center assignment, select the assignment, and then click Remove.
4. To modify a data center assignment, select the assignment, and then click Modify. Enter the new
Data center name in the Modify Node in Data Center List window, and then click OK.
5. To add a data center assignment, click Add. Select a host and a data center, and then click OK.
6. Click OK to save your changes and close the window.
Changing failover and failback behavior
1. Open Cluster Administrator and double-click the resource you want to edit.
2. Click the Parameters tab.
XP Cluster Extension Software Administrator Guide 51