HP StorageWorks SAN Director Installation Guide (A7393-90009, May 2007)

SAN Director installation guide 39
Table 6 Installation tasks, time and items required
Installation Task Time Estimate Items Required
Unpacking the Director 30 minutes 1/2-in. socket wrench (to remove pallet
bolts)
#2 Phillips screwdriver
(for cable management comb)
Pallet jack
Hydraulic lift or assisted lift, able to raise to
a minimum of 55 in. (140 cm), with a
minimum capacity of 113 kg (250 lb). The
4/256 SAN Director weighs 98 kg (216 lb)
without media but can weigh considerably
more depending on the media installed.
Installing rack mount kit 30 minutes See ”Installing the switch in a rack”.
Mounting and securing Director in rack 30 minutes
Installing power cables and serial cable
and configuring IP addresses
20 minutes Power cables and serial cable (provided in
4/256 SAN Director accessory kit)
Workstation computer with a serial port or
terminal server port and a terminal
emulator application (such as
HyperTerminal)
Ethernet IP addresses for the switch (1) and
for each CP blade (2): total three addresses
Installing Ethernet cable(s) and
configuring the 4/256 SAN Director
name, policies, domain ID, PIDs, or
additional system parameters
20 minutes Ethernet cabling (optional) is required for
telnet access. All other configuration
parameters optional.
See the HP StorageWorks Fabric OS
administrator guide for PID information.
Installing SFP optical transceivers 30 minutes SFP optical transceivers
Attaching fiber optic cables, cable ties,
and cable guides
60 minutes Fiber optic cables, cable ties, and cable
pillars