Site Preparation Guide, Third Edition - Server Expansion Unit
Appendix A
General Site Preparation Guidelines
Example of an Installation Schedule
35
Example of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
• 60 days before installation
— Floor plan design completed and mailed to HP (if required to be an HP task)
• 30 days before installation
— Primary power and air-conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— A signed copy of the site inspection and delivery survey mailed to HP
— Site inspection and pre-delivery coordination meeting arranged with a HP representative to review
the inspection checklist and arrange an installation schedule
• 7 days before installation
— Final check made with an HP site preparation specialist to resolve any last minute problems
NOTE Not all installations follow a schedule like the one previously noted. Sometimes a server is
purchased through another vendor, which can preclude a rigid schedule. Other conditions could
also prevent following this schedule. For those situations, consider a milestone schedule.
• Site Preparation—schedule with the customer as soon as possible after the order is placed.
• Site Verification—schedule with the customer a minimum of one to two days before the
product is scheduled to be installed.