HP Cluster Platform Site Preparation Guide

Table A-2 Site Inspection Worksheet (continued)
Comment or DateCheckItem
Is the dedicated branch circuit less than 250 ft (72.5
m)?
Are the input circuit breakers adequate for
equipment loads?
Safety
Is there an emergency power shut-off switch?
Is there a telephone available for emergency
purposes?
Is there a fire protection system in the computer
room?
Is antistatic flooring installed? What other ESD
prevention is in place?
Are there any equipment servicing hazards (loose
ground wires, poor lighting, etc.)?
Cooling
Can cooling be maintained within the parameters
specified for or calculated for the cluster?
Can temperature changes be held to 9° (5°C) per
hour?
Can humidity level be maintained between 40% and
55%?
Are air conditioning filters installed and clean?
A.4 Delivery Survey
The delivery survey lists delivery or installation requirements. Special instructions or
recommendations should be noted, as appropriate. Following are examples of special instructions
or issues:
Packaging restrictions at the facility, such as size and weight limitations
Equipment required for installation, such as tracking or hoists
What time the facility is available for installation (after the equipment is unloaded)
Security requirements applicable to the facility, such as security clearance
Use the worksheet in Table A-3 to complete the delivery survey.
Table A-3 Delivery Survey Worksheet
Delivery Dock
Provide the location of the dock, including an address
if it is different from the installation site.
NotesCheckDock Checklist
NYIs the dock adequate for the trailer?
NYHeight of access door checked.
48 Planning Checklist