HP StoreOnce B6200 Installation Planning and Preparation Guide (EJ022-90995, November 2013)

Table 14 Product configuration (continued)
Note any requirements for:
Capacity upgrades and licenses
Replication and Catalyst licenses
Security license (available with StoreOnce software v3.9.0 and later)
Couplet(s) to be installed
Additional cabling requirements and make sure they are pre-laid
Location
At the time of placing the order, make sure that there is a suitable location with access to install
the product. This must be a data center environment and not an office environment. (See Product
specifications (page 8) for more details.) It should conform to the following requirements:
The receiving dock, storage area, and receiving area are large enough to allow movement of
and access to crated or packed equipment.
1.
The floors, elevators, and ramps are able to support the weight of the delivered equipment as it
is moved to the installation location.
2.
The installation location must provide:3.
Sufficient space to accommodate the installed product. This product is provided in extended
racks: an installed depth of 1240mm ( 50.50 inches ) is required.
nl
Note: When installing two racks, the units should be located next to each other, to ensure there
are no problems with cable lengths.
Appropriate power, air conditioning, cabling, and fire protection.
Adequate protection from electrostatic discharge (ESD).
Adequate protection from electrical/radio frequency interference.
Adequate protection from dust, pollution, and particulate contamination
Adequate acoustic insulation for operating the system.
Power/PDU requirements
At the time of placing the order, make sure that the location can support the HP B6200 Backup
System’s input power and power outlet requirements. The AC power input for the HP B6200 Backup
System has a duplex PDU structure, which enables the entire rack to remain powered on if power
is removed from one of the two power distribution panels.
Prior to installation you should confirm that you have specified the correct PDU for your geographical
location and connector type and that you have sufficient power outlets. See Power/PDU
requirements (page 9).
26 Checklists for completion prior to installation