Table 18 Three possible critical resource analysis (CRA) outcomes (continued)
User ActionsButtons ActivatedScreen DisplaysNotesOutcome
your knowledge of
the current system
configuration.
SMH displays a dialog indicating that the selected slot has power disabled and it is now safe
to add the card to the desired slot.
9. At this point, the amber LED is activated and the green LED is off. Now add the new PCI card.
Refer to the system manual for the insertion of the PCI card.
NOTE: Do not connect the cables to the card at this point
10. Once you have inserted the new card, return to the console and click OK on the dialog,
assuming there is one. At this point, SMH will:
• return power to the card slot and enable power to the Green LED
• attach drivers by running ioscan on the new hardware
• update the list of cards and slots on the system shown in the I/O cards area
NOTE: At this point, the OLA is complete. Note that in some cases additional configuration
in another area of SMH may also be required. A network interface card, for example, might
require network parameter setup in the Network Interface Card portion of the Networking
and Communications area.
11. If the OLA is successful, connect the cables to the card.
76 OLA/R overview and concepts