— 1 ft. = 0.305 m
— 1 CFM = 1.7m3/h
kVA Conversions
Three phase
kVA = V × A × √3 / 1000
Single phase
kVA = V × A / 1000
Formulas
kVA = Voltage x Current (amps)
Watts = VA x PF
BTU = Watts x 3.41
Example of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
60 days before installation
— Floor plan design completed and mailed to Hewlett-Packard (if required to be an HP
task)
30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— A signed copy of the site inspection and delivery survey mailed to Hewlett-Packard
— Site inspection and predelivery coordination meeting arranged with a Hewlett-Packard
representative to review the inspection checklist and arrange an installation schedule.
7 days before installation
— Final check made with an Hewlett-Packard site preparation specialist to resolve any
last minute problems
NOTE: Not all installations follow a schedule like the one noted above. Sometimes, a server is
purchased through another vendor, which can preclude a rigid schedule. Other conditions could
also prevent following this schedule. For those situations, consider a milestone schedule.
Site Preparation—schedule with the customer as soon as possible after the order is placed.
Site Verification—schedule with the customer a minimum of one to two days before the
product is scheduled to be installed.
Sample Site Inspection Checklist
Table 2-5 and Table 2-6 provide sample checklists. Enter the appropriate information in the areas
provided.
Example of an Installation Schedule 43