NonStop NS-Series Planning Guide (H06.03+)

System Installation Planning
HP Integrity NonStop NS-Series Planning Guide529567-004
7-5
Process
Process
1. Inspect and mark either the Yes, No or RISK box in each line item.
Provide an explanation in the comments area for all items marked as RISK. Some
No replies might require an explanation for clarification.
2. Ensure all items are completed.
3. For questionable items, contact the appropriate Data Center Services group, such
as a Data Center Thermal Analysis.
An item deemed as a RISK can impact the installation and or stability of the system.
Take necessary action or make appropriate recommendations to mitigate the risk.
Example Site Inspection Report Form
The example site inspection report form includes:
Topic Page
Computer Room
7-6
Power and Lighting 7-8
Safety 7-11
Air Conditioning 7-12
EMI and RFI 7-13
Storage 7-14
Building Access, Security, and Equipment Delivery 7-15
Communication 7-18
Floor Plan 7-19