NonStop NS-Series Planning Guide (H06.03+)

System Installation Planning
HP Integrity NonStop NS-Series Planning Guide529567-004
7-16
Building Access, Security, and Equipment Delivery
G-18 Is door/elevator height requirement of 90 inch for racked
delivery?
? ? ?
G-19 Is the path from loading bay to computer room robust
enough to support the weight of the equipment?
(see product specifications)
? ? ?
G-20 Will the equipment fit through all doors, corridors and
elevators, both in size and weight without tilting?
? ? ?
G-21 Are there any ramp angles or thresholds that are of
concern?
? ? ?
G-22 Are floor finishes along the delivery route acceptable
(hard and smooth) for rolling the equipment across?
(will the floor surface need to be covered before
moving the equipment over it)
? ? ?
G-23 Is the path onto raised floor rated for dynamic loading of
server?
? ? ?