NonStop NS1000 Planning Guide (H06.07+)

Example Configurations
HP Integrity NonStop NS1000 Planning Guide542527-003
7-12
Example of 2-Processor System Cabling
Example of 2-Processor System Cabling
This illustration shows an example of a 2-processor system. This conceptual
representation shows the simplified X and Y ServerNet cabling between the blade
elements and the IOAM enclosure and also the simplified cabling between the FCSAs
and the Fibre Channel disk modules. The example of Fibre Channel disk module
configuration for the group 100 IOAM enclosure is described in more detail in Two
FCSAs, Two FCDMs, One IOAM Enclosure on page 6-16.
To simplify the illustration, power and Ethernet cables are not shown. For cable-by-
cable interconnect diagrams, see Internal ServerNet Interconnect Cabling on page 6-4.
Cable management hardware that is part of each modular enclosure and also the rack
is not shown. Therefore, actual cable routing using the cable management hardware is
different from that shown. For detailed information on cable routing, refer to the
NonStop NS-Series Hardware Installation Manual.
VST.305.vsd
IOAM
100.2
IOAM
100.3
FCDM
P1
FCDM
M1