H06.05 Software Installation and Upgrade Guide

Installing a SUT for the H06.05 RVU
H06.05 Software Installation and Upgrade Guide541762-003
4-6
Create a New Software Revision
Create a New Software Revision
When you create a new software revision, DSM/SCM selects the products in the SUT
that are licensed for your site and replaces any previous versions of the products.
The following steps assume that you are creating a new software revision that
manages OSS files. If you are not, go to step 6 after you are in the Planner Interface
Configuration Revisions window. These instructions also assume that you have
installed OSS. To configure OSS for the first time, see the Open System Services
Installation Guide. For details on modifying a DSM/SCM target, see the DSM/SCM
User’s Guide.
1. Check that the OSS Root Name Server $ZPNS is running on the Target. The
volume where the SYSnn is being placed must be activated as $SYSTEM to install
OSS files. To determine the server process, issue an SCF STATUS SERVER
command or an SCF LISTDEV command. An example of the STATUS SERVER
command is:
$ADBIT TESTBIT 11> SCF STATUS SERVER $ZPMON.*
SCF - T9082H01 - (01MAY05) (15MAR05) - 07/06/2005 08:58:59 System \ATLAS
(C) 1986 Tandem (C) 2003 Hewlett Packard Development Company, L.P.
OSS Status SERVER \ATLAS.$ZPMON.*
ServerName State LastError ErrorDetail
#ZMSGQ STARTED 0 0
#ZPLS STARTED 0 0
#ZPNS STARTED 0 0
#ZTA00 STARTED 0 0
#ZTA01 STARTED 0 0
#ZTA02 STARTED 0 0
#ZTA03 STARTED 0 0
#ZTA04 STOPPED 0 0
#ZTA05 STOPPED 0 0
#ZTA06 STOPPED 0 0
#ZTA07 STOPPED 0 0
#ZTA08 STOPPED 0 0
#ZTA09 STOPPED 0 0
#ZTA10 STOPPED 0 0
#ZTA11 STOPPED 0 0
#ZTA12 STOPPED 0 0
#ZTA13 STOPPED 0 0
#ZTA14 STOPPED 0 0
#ZTA15 STOPPED 0 0
Total Errors = 0 Total Warnings = 0
$ADBIT TESTBIT 12>
2. In the DSM/SCM Planner Interface, in the Configuration Revisions dialog box,
select the target configuration.
3. Select Maintain>Target Maintenance>Modify.
a. Check that the Manage OSS Files option is selected.