Site Preparation Guide - HP Integrity rx1620
General Site Preparation Guidelines
Sample of an Installation Schedule
Chapter 3
35
Three phase
kVA = V × A × √3 ⁄ 1000
•Single phase
kVA = V × A ⁄ 1000
Formulas
• kVA = Voltage x Current (amps)
• Watts = VA x PF
• BTU = Watts x 3.41
Sample of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
• 60 days before installation
— Floor plan design completed and mailed to Hewlett-Packard (if required to be an HP task)
• 30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— A signed copy of the site inspection and delivery survey mailed to Hewlett-Packard
— Site inspection and predelivery coordination meeting arranged with a Hewlett-Packard
representative to review the inspection checklist and arrange an installation schedule.
• 7 days before installation
— Final check made with an Hewlett-Packard site preparation specialist to resolve any last minute
problems
NOTE Not all installations follow a schedule like the one noted above. For those situations, consider a
milestone schedule.
• Site Preparation—schedule with the customer as soon as possible after the order is placed.
• Site Verification—schedule with the customer a minimum of one to two days before the hp
Integrity rx1620 Server is scheduled to be installed.