Site Preparation Guide. First Edition - HP Integrity rx2620 Server (August 2006)

General Site Preparation Guidelines
Sample of an Installation Schedule
Chapter 2
34
Sample of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
60 days before installation
Floor plan design completed and mailed to Hewlett-Packard (if required to be an HP task)
30 days before installation
Primary power and air conditioning installation completed
Telephone and data cables installed
Fire protection equipment installed
Major facility changes completed
Special delivery requirements defined
Site inspection survey completed
Delivery survey completed
A signed copy of the site inspection and delivery survey mailed to Hewlett-Packard
Site inspection and predelivery coordination meeting arranged with a Hewlett-Packard
representative to review the inspection checklist and arrange an installation schedule.
7 days before installation
Final check made with an Hewlett-Packard site preparation specialist to resolve any last minute
problems
NOTE Not all installations follow a schedule like the one noted above. Sometimes, an hp Integrity
rx2620 Server is purchased through another vendor, which can preclude a rigid schedule. Other
conditions could also prevent following this schedule. For those situations, consider a milestone
schedule.
Site Preparation—schedule with the customer as soon as possible after the order is placed.
Site Verification—schedule with the customer a minimum of one to two days before the hp
Integrity rx2620 Server is scheduled to be installed.