Site Preparation Guide, Second Edition - HP Integrity rx4640 Server
General Site Preparation Guidelines
Sample of an Installation Schedule
Chapter 2
39
Sample of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
• 60 days before installation
— Floor plan design completed and mailed to Hewlett-Packard (if required to be an HP task)
• 30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— A signed copy of the site inspection and delivery survey mailed to Hewlett-Packard
— Site inspection and predelivery coordination meeting arranged with a Hewlett-Packard
representative to review the inspection checklist and arrange an installation schedule.
• 7 days before installation
— Final check made with an Hewlett-Packard site preparation specialist to resolve any last-minute
problems
NOTE Not all installations follow a schedule like the one noted above. Sometimes, an hp Integrity
rx4640 server is purchased through another vendor, which can preclude a rigid schedule. Other
conditions could also prevent following this schedule. For those situations, consider a milestone
schedule.
• Site Preparation—schedule with the customer as soon as possible after the order is placed.
• Site Verification—schedule with the customer a minimum of one to two days before the hp
Integrity rx4640 server is scheduled to be installed.