Site Preparation Guide, Fourth Editon - HP Integrity rx7620 Server
Appendix B
General Site Preparation Guidelines
Sample of an Installation Schedule
56
Sample of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
• 60 days before installation
— Floor plan design completed and mailed to HP (if required to be an HP task)
• 30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— A signed copy of the site inspection and delivery survey mailed to HP
— Site inspection and predelivery coordination meeting arranged with a HP representative to review
the inspection checklist and arrange an installation schedule.
• 7 days before installation
— Final check made with an HP site preparation specialist to resolve any last minute problems
NOTE Not all installations follow a schedule like the one noted above. Sometimes, a server is
purchased through another vendor which can preclude a rigid schedule. Other conditions could
also prevent following this schedule. For those situations, consider a milestone schedule.
• Site Preparation - schedule with the customer as soon as possible after the order is placed.
• Site Verification - schedule with the customer a minimum of one to two days before the
product is scheduled to be installed.