HP Modular Cooling System Generation 2 site preparation guide - Technical white paper
10
Figure 4 shows the maneuvering space required when unloading the HP MCS G2 (in a single IT
rack configuration) from a pallet. Use the delivery forms provided in appendix A when planning for
unit maneuvering.
Figure 4: HP MCS G2 shipping package delivery and maneuvering space requirements for a single IT rack configuration
Caution:
It is recommended that a ramp angle of no greater than 5° be used to
move the HP MCS cabinet up or down elevations. Typical data center
ramps have a 5º angle (1 to 12 pitches).