HP Modular Cooling System Site Preparation Guide
Pre-Installation Checklists
Site Preparation Checklist
Table 12 is a site preparation checklist. For each item, please check yes or no in the appropriate
column. If answering “No,” include a comment and the date. A “No” answer means that an
alternative may be required.
Table 12 Site Preparation Checklist
Item
Area/
Condition
Yes No Comment/Date
Facility Considerations
1
Is there a completed floor plan, including a
detailed location of the MCS relative to the
floor tile breaks and supports
2
Is there adequate space for maintenance needs?
Front 48 in. (1219 mm) minimum, rear 36 in. (914
mm) minimum are recommended clearances.
3 Is access to the site or computer room restricted?
4
Is the computer room structurally complete? Expected
date of completion?
5 Is a raised floor installed and in good condition?
6
Is the raised floor system, including needed
cutouts, able to adequately support the fully
loaded rack and MCS?
7 Are there channels or cutouts for cable routing?
8 Is there a network line available?
9 Is a telephone line available?
10
Are floor tiles in good condition and properly
braced?
11
Is there a leak detector for the chilled water
system(external to the HP MCS)
Power and Lighting Considerations
12
Are there AC outlets available for servicing needs?
(for example, laptop)
13
Does the input voltage correspond to HP MCS
specifications?
14
Is dual source power used? If so, identify types and
evaluate grounding.
15
Does the input frequency correspond to equipment
specifications?
16 Is power conditioning equipment installed?
17 Is there a dedicated branch circuit for equipment?
HP MCS Site Preparation Guide
49