HP Modular Cooling System Site Preparation Guide

Item
Area/
Condition Yes No Comment/Date
18
Is the dedicated branch circuit less than 75 feet
(22.86 meters) away?
19
Are the input circuit breakers sized to protect their
respective receptacles for equipment loads?
Safety Considerations
20 Is there an emergency power shutoff switch?
21
Is there a telephone available for emergency
purposes?
22
Is there a fire protection system in the computer
room?
23 Is antistatic flooring installed?
Cooling Considerations
24
Can the room temperature be maintained between
the recommended 68°F (20° C) Min. – 77° F (25° C)
Max. and allowable 59° F (15° C) Min. – 90° F
(32° C) Max. (up to 5000 ft.) Derate 1 degree
C/1000 ft. above 5000 ft. and up to 10,000 ft.
25
Can humidity level be maintained at the
recommended level of 40% to 50%, with an
allowable humidity levels of 20% to 60%
26 Are air-conditioning filters installed/clean?
Water Preparation Considerations
27
Has the water been tested for acceptable quality for
use in the HP Modular Cooling System unit?
28
If the water quality is unacceptable, have adequate
treatment and filtration measures been put into
place?
29
Have the water temperature and flow been
evaluated?
30
If temperature and flow are not adequate, have
supplemental chiller units and water pumps been
implemented to achieve ample performance?
31
Has an adequately sized water-to-water heat
exchanger been implemented to provide an
dedicated water loop to the HP Modular Cooling
System units?
32
Has piping of an appropriate diameter, material,
and pressure tolerance been installed to reach the
back of each HP MCS?
33
Is there a provision for fluid collected from the
condensation and overflow hoses at each HP
Modular Cooling System unit?
HP MCS Site Preparation Guide
50