9710 (StorageTek) Addendum for NonStop Servers

Addendum tot he StorageTek 9710 for the Tandem Environment
Configuring the 5155/5159 Digital Linear Tape FRU for the Himalaya S-series Servers
7-21
2. Connect the power cord to the 5155/5159 power connector.
Make sure connector is fully seated.
3. Connect the other end of the power cord to a Power Distribution
Unit (PDU) AC outlet contained in the 9710 Automated Cartridge
Subsystem.
7.12 Test the Installation
Section 2.6, page 2-11, describes how to test the 5155/5159 Tape FRU
after installation. It includes the Power-On Self-test (POST) and
what occurs during and after POST.
POST completes in about 13 seconds and the drive responds normally
to all commands. However, it might take longer for the media to become
ready. After a bus reset, the tape drive responds within a bus selection
time-out period.
7.12.1 What to Do after POST
Table 7-3 After POST
If… Then…
All the events in Table 2-2 took place POST succeeded. Use SCF to bring up
the System and run optional TMDS tests
All left-side or right-side lights on the
5155/5159 front panel blink only.
POST failed. See Table 2-4