NonStop S-Series Hardware Installation and FastPath Guide (G06.29+)
Installing Enclosures
HP NonStop S-Series Hardware Installation and FastPath Guide—541880-002
2-3
2. Prepare the Work Space
2. Prepare the Work Space
1. Clear the installation site so that you have room to work.
2. Use the Floor Plan Diagram to find the installation site or sites.
3. Verify that preinstalled I/O device cables, such as Ethernet LAN cables, are
installed:
•
For a list of cables, see the Preinstalled I/O Device Cable Checklist.
•
To find the preinstalled cables, use the Floor Plan Diagram.
4. Report any missing cables to the system planner.
5. Ensure that the installation site provides adequate electrical connections.
Connections include:
•
Two properly grounded outlets for each system enclosure to be installed
•
One branch circuit breaker for each outlet
•
Emergency power-off (EPO) disconnect wiring
This requirement applies only to computer room installations in the United
States or installations governed by local regulations that stipulate EPO
capability.
For more information about EPO requirements, see the NonStop S-Series
Planning and Configuration Guide.
•
One single-source distribution, uninterruptible power supply (UPS))
Connect the entire system to the UPS. For more information about UPS
requirements, see the NonStop S-Series Planning and Configuration Guide.
6. Ensure the AC power cords for the enclosures to be installed are correct for the
outlets at the installation site:
•
For a list of supported AC power cords by country, plug type, part number, and
length for system enclosures, see the Part Numbers topic of the Service
Information section of the NTL Support and Service Library. See Support and
Service Library on page xxiv.
•
For power planning information, see the NonStop S-Series Planning and
Configuration Guide.