Completing the Installation Plan
This section describes how to finish the planning tasks described in this guide,
including preparing an Installation Document Packet containing forms and worksheets
that describe how to arrange the enclosures, what hardware is present, and what
cables are required to build your system:
Create the Installation Schedule
Create the installation schedule based on all of the planning you have done. Ensure
that:
Before the equipment is delivered, the installation site is prepared.
After the equipment arrives, time is allowed to:
°
Test the system
°
Create and test the operational environment
Create the Installation Schedule 13-1
Assemble the Installation Document Packet 13-2
Installation Document Checklist 13-3
System Equipment Inventory Form 13-5
Enclosure Arrangement Diagram 13-7
Floor Plan 13-9
Preinstalled I/O Device Cable Checklist 13-11
System Enclosure Checklist 13-13
PMF CRU Configuration Forms 13-16
IOMF CRU Configuration Forms 13-20
ServerNet Adapter Configuration Forms 13-22
ServerNet Cluster Configuration Form 13-22
ServerNet Cabling Forms 13-23
Cross-Row Cabling Worksheets 13-25
IOAM Worksheets 13-26
Final Planning Checklist 13-27
Finish Planning 13-28
Note. Not all the products, configurations, features, and functions described in this guide are
available with the current RVU. Ask your HP representative about the availability of these prod-
ucts, configurations, features, and functions.