ServerNet Cluster 6770 Hardware Installation and Support Guide

Installing Switch Components in an EIA Standard
Rack
ServerNet Cluster 6770 Hardware Installation and Support Guide522544-002
5-3
Task 1: Assemble the Required Tools
Task 1: Assemble the Required Tools
You need the following tools:
Cage-nut fitting tool
T25 Torx screwdriver
T20 Torx screwdriver
7 mm wrench
Phillips screwdriver
Nut driver
Task 2: Verify That You Have All the Parts in
the Rack-Mount Kit
The rack-mount kit contains the following parts:
Quantity Description
1 UPS left fixed rail
1 UPS right fixed rail
2 UPS rail brackets
1 Cable-management tray
4 ServerNet II Switch slide rail brackets
2 ServerNet II Switch slide rails
2 Cable-management assembly arms
1 Cable-management assembly bracket
20 M5 Torx screws
14 Cage nuts
10 8-32X.375 kep nuts
8 8-32X.375 Flat-head Phillips screws
3 Blank panels
1 package Cable labels
1 package Numeric labels for the ServerNet II Switch
1 package Alphabetic labels for the ServerNet II Switch