ServerNet Cluster 6770 Hardware Installation and Support Guide
Installing Switch Components in an EIA Standard
Rack
ServerNet Cluster 6770 Hardware Installation and Support Guide—522544-002
5-9
Task 8: Connect and Route the Cables and Cords
4. Push the ServerNet II Switch into the rack.
5. Pull the ServerNet II switch out slowly to make sure that the slide lock catches.
Make sure that the ServerNet II Switch slides in and out easily.
6. Leave the ServerNet II Switch fully extended during the rest of the installation.
Task 8: Connect and Route the Cables and
Cords
1. Connect an AC power cord from the outlet on the UPS to the AC power inlet on the
ServerNet II switch.
2. Use two cable ties to the fasten the AC power cord to the base of the ServerNet II
Switch.
3. Connect an AC power cord from the IEC-320 inlet on the UPS to exposed power
outlet on the AC transfer switch.
4. Connect the 36-inch power-monitor cable from the AC transfer switch to the
monitor port on the UPS.
5. Connect the 84-inch power-monitor cable from AC transfer switch to the monitor
port on the ServerNet II Switch.
6. Connect the cables to the nodes as described in Section 6, Connecting the
ServerNet Fiber-Optic Cables.
Task 9: Power On the Components
Refer to Powering On a ServerNet Cluster Switch on page 7-2.
Figure 5-3. Rear Panel of the UPS
Power
Outlet
Monitor
Port
REPO
Port
IEC-320
Inlet
VST901.vsd