ServerNet Cluster 6780 Planning and Installation Guide (G06.24+, H06.03+)

Connecting the Fiber-Optic Cables
ServerNet Cluster 6780 Planning and Installation Guide527301-004
6-4
Connecting the Layer Cables
Connecting the Layer Cables
To connect the fiber-optic cables between layers of 6780 switches in a group:
1. Inventory the hardware. For more information, refer to Task 7: Plan for the Fiber-
Optic Cables on page 3-15.
a. Check that you have the correct number of layer cables.
b. Check that you have the correct type of cables in the required lengths.
2. Label both ends of each fiber-optic cable. Refer to Layer Cable Connections on
page 6-5.
On each label, include the fabric, zone, and layer of the switch, and the slot
number, and port number the cable will be connected to. For example, switch X12,
slot 12, port 1 on one end of the cable and switch X14, slot 12, port 1 on the other
end.
3. Connect the fiber-optic cables between the zones. Refer toConnect the Layer
Cables on page 6-9