ServerNet Cluster 6780 Planning and Installation Guide (G06.24+, H06.03+)
Preparing a System for Installation or Migration
ServerNet Cluster 6780 Planning and Installation Guide—527301-004
4-2
Task 1: Complete the Planning Checklist
Task 1: Complete the Planning Checklist
Before you install or migrate a ServerNet cluster or add a node to the cluster, complete
all the tasks in the planning checklist in Planning Checklist on page 3-2. Also refer to
the Switch Planning Form on page B-2.
Task 2: Install the Servers
If the individual servers are not already installed, you must install them and ensure that
they function properly as stand-alone systems before adding them to a cluster. You can
install all the servers now or install them individually before adding each one to the
cluster.
To plan for installation and to install a NonStop S-Series server, refer to:
•
NonStop S-Series Planning and Configuration Guide
•
NonStop S-Series Hardware Installation and FastPath Guide
Table 4-1. Task Summary for Preparing a System
√ Description Page
Task 1: Complete the Planning Checklist
4-2
Task 2: Install the Servers 4-2
Task 3: Check and Install the Required Software 4-3
Task 4: Check Operations and the Required Processes 4-5
Task 5: Check and Install the Hardware 4-6
Note. If you do not complete the planning checklist, you might have to go back and complete
some planning tasks during installation.