ServerNet Cluster 6780 Planning and Installation Guide (G06.28+, H06.05+)

Table Of Contents
Connecting the Fiber-Optic Cables
ServerNet Cluster 6780 Planning and Installation Guide527301-005
6-6
Layer Cable Connections
Figure 6-2 on page 6-6 shows X-fabric cable connections for three layers in zone 1.
Connections for the Y fabric and for zones 2 and 3 are the same. With three layers in
each zone, these slots contain blank PICs:
Slot 13 in layer 1
Slot 12 in layer 2
Slot 11 in layer 3
Figure 6-2. Cable Connections for Three Layers
Slot 11 Slot 12 Slot 13
4
3
2
1
4
3
2
1
Slot 11 Slot 12 Slot 13
4
3
2
1
4
3
2
1
Slot 11 Slot 12 Slot 13
4
3
2
1
4
3
2
1
X13
X12
X11
VST302.vsd