- 3 Planning for Installation and Migration
- Planning Checklist
- Software Installation Planning
- Hardware Installation and Migration Planning
- Task 1: Plan for the ServerNet Nodes
- Task 2: Plan for the System Consoles
- Task 3: Plan for the 6780 Switches
- Task 4: Plan for the Racks
- Task 5: Plan for the Power Requirements
- Task 6: Plan the Location of the Hardware
- Task 7: Plan for the Fiber-Optic Cables
- Task 8: Plan to Migrate the ServerNet Nodes From 6770 Switches
- Task 9: Plan the ServerNet Node Numbers
- Task 10: Plan the Expand-Over-ServerNet Lines
- Migration Examples
- 4 Preparing a System for Installation or Migration
- 5 Installing 6780 Switches
- 6 Connecting the Fiber-Optic Cables
- Summary of Tasks
- Handling the Fiber-Optic Cables
- Connecting the Layer Cables
- Connecting the Zone Cables
- Connecting the Cables Between a Node and a 6780 Switch
- Alerts
- Task 1: Double-Check the Required Software and Hardware
- Task 2: Label the Cables That Connect to the Node
- Task 3: Inspect the Cables
- Task 4: Connect a Cable to the Switch
- Task 5: Connect a Cable to the Node
- Task 6: Check the Link-Alive LEDs
- Task 7: Check Operations
- Task 8: Finish Connecting the Fiber-Optic Cables
- Routing the Fiber-Optic Cables
- 7 Configuring Expand-Over-ServerNet Lines
- Using Automatic Line-Handler Generation
- Using the OSM Service Connection
- Using SCF
- Rule 1: Configure the Primary and Backup Line-Handler Processes in Different Processor Enclosures
- Rule 2: For Nodes With 6 or More Processors, Avoid Configuring the Line-Handler Processes in Proc...
- Rule 3: For Nodes With More Than 10 Processors, Avoid Configuring the Line-Handler Processes in P...
- Expand-Over-ServerNet Line-Handler Process Example
- 8 Checking Operations
- Checking the Operation of the ServerNet Cluster
- Checking the Operation of Each Switch
- Checking the Power to Each Switch
- Checking the Switch Components
- Checking the Numeric Selector Setting
- Checking the Globally Unique ID (GUID)
- Checking for a Mixed Globally Unique ID (GUID)
- Checking the Fiber-Optic Cable Connections to the Switch Port
- Checking the Switch Configuration, Firmware, and FPGA Images
- Checking the Operation of Each Node
- Checking the Service Processor (SP) Firmware
- Checking That Automatic Line-Handler Generation Is Enabled
- Checking the ServerNet Node Numbers
- Checking MSGMON, SANMAN, and SNETMON
- Checking for Alarms on Each Node
- Checking the ServerNet Cluster Subsystem
- Checking That the ServerNet Node Numbers Are Consistent
- Checking Communications Between a Local Node and a Switch
- Checking Communications With a Remote Node
- Checking the Internal ServerNet X and Y Fabrics
- Checking the Operation of Expand Processes and Lines
- 9 Changing a ServerNet Cluster
- OSM Actions
- Removing a Node From a ServerNet Cluster
- Removing Switches From a ServerNet Cluster
- Adding a Node to a ServerNet Cluster
- Adding a Switch Layer to a ServerNet Cluster
- Adding a Switch Zone to a ServerNet Cluster
- Task 1: Prepare to Add the Switches
- Task 2: Connect the Cables Between Layers
- Task 3: Check Operations
- Task 4: Disconnect the Cables Between Zones
- Task 5: Connect the Cables Between Zones
- Task 6: Check Operations
- Task 7: Connect the Additional Nodes
- Task 8: Check Operations
- Task 9: Repeat Tasks 2 Through 8 for the Other Fabric
- Task 10: Reenable OSM Alarms
- Moving a Node
- Changing the Hardware in a Node Connected to a ServerNet Cluster
- 10 Troubleshooting
- Symptoms
- Recovery Operations
- Enabling Automatic Expand-Over-ServerNet Line-Handler Generation
- Reseating a Fiber-Optic Cable
- Correcting a Mixed Globally Unique ID (GUID)
- Restoring Connectivity to a Node
- Switching the SANMAN Primary and Backup Processes
- Switching the SNETMON Primary and Backup Processes
- Configuring the Expand-Over-ServerNet Line-Handler Processes and Lines
- Starting Required Processes and Subsystems
- Fallback Procedures
- 11 Starting and Stopping ServerNet Cluster Processes and Subsystems
- A Part Numbers
- B Blank Planning Forms
- C ESD Guidelines
- D Specifications
- E Configuring MSGMON, SANMAN, and SNETMON
- F Updating the 6780 Switch Logic Board Firmware, Configuration, and FPGA Images
- G Using the Long-Distance Option
- Safety and Compliance
- Glossary
- Index

Planning for Installation and Migration
ServerNet Cluster 6780 Planning and Installation Guide—527301-005
3-3
Planning Checklist
For the best fault tolerance, check that the
uninterruptible power supplies are available to
support the 6780 switches.
Task 5: Plan for the Power
Requirements on page 3-13
Plan for the Hardware Hardware Installation and
Migration Planning on page 3-5
Plan for the Nodes
If the servers are not already installed, check that
the preinstallation planning for the servers and
peripheral equipment is conducted in accordance
with the required standards.
NonStop S-Series Planning and
Configuration Guide
Check that no more than 96 servers are
connected to a ServerNet cluster.
Task 1: Plan for the ServerNet
Nodes on page 3-5
For each NonStop S-series server to join the
ServerNet cluster, check that MSEBs are installed
in slots 51 and 52 of the group 01 system
enclosure.
Installing the Required
Hardware in NonStop S-Series
Servers on page 4-10
For the MSEBs in slots 51 and 52 of group 01 of
each NonStop S-series server, check that the
MSEBs contain a SMF PIC with the NNA FPGA in
port 6.
Installing the Required
Hardware in NonStop S-Series
Servers on page 4-10
If MSEBs are to be installed in a NonStop S-series
server, check that ServerNet cables with the
appropriate connectors are available to connect
the MSEBs to other system enclosures.
NonStop S-Series Planning and
Configuration Guide
Plan for the System Consoles
Check that an adequate number of system
consoles are available to manage the nodes in the
cluster.
Task 2: Plan for the System
Consoles on page 3-6
Plan for the Switches
Check that the 6780 switches are either available
or ordered.
Task 3: Plan for the 6780
Switches on page 3-8
Check that the PICs for each 6780 switch are
either available or ordered.
Plan the PICs Needed for Each
6780 Switch on page 3-10
Plan for the Racks
Check that enough 19-inch racks are available for
the 6780 switches and other components. If you
are providing your own racks, check that they
meet the required specifications.
Task 4: Plan for the Racks
on
page 3-12
Check that there is enough floor space to
accommodate the footprint of each 19-inch rack.
Floor Space for the Racks
on
page 3-12.
Table 3-1. Planning Checklist (page 2 of 3)
√ Major Planning Step For More Information