Task 3: Plan for the 6780 Switches
Plan the PICs Needed for Each 6780 Switch
Blank PICs are installed if other PICs are not present.
1. If you have two or three zones, decide whether to use two dual SMF PICs or two
quad MMF PICs for the zone interconnect.
2. Decide on the number of dual SMF PICs for the connection between a 6780 switch
and a NonStop S-series server. You must have at least the minimum number
stated in Table 3-4.
Table 3-4. PICs in 6780 Switch
Slots Function PIC Type
Minimum Number of PICs
Required for Each 6780
Switch Blank PICs
Slot 1 N.A. Maintenance 1 None
Slots 2
and 3
Zone
Interconnect
Dual SMF 1 zone: 0
2 or 3 zones: 2
1 zone: 2
2 or 3 zones: 0
Quad MMF 1 zone: 0 1 zone: 2
2 or 3 zones: 2 2 or 3 zones: 0
Slots 4,
5, and
10
Router
Interconnect
Router
Interconnect
3 None
Slots 6
through
9
Node
Interconnect
Dual SMF
(connections
between a
6780 switch
and a
NonStop
S-series
server only)
2 NonStop S-series servers: 1
4 NonStop S-series servers: 2
6 NonStop S-series servers: 3
8 NonStop S-series servers: 4
1 for each slot
not occupied
by other PICs
Slots 11
through
13
Layer
Interconnect
Quad MMF 1 layer: 0
2 layers: 1
3 layers: 2
4 layers: 3
1 layer: 3
2 layers: 2
3 layers: 1
4 layers: 0