ServerNet Cluster 6780 Planning and Installation Guide (G06.29+, H06.06+, J06.03+)
Planning for Installation and Migration
ServerNet Cluster 6780 Planning and Installation Guide—527301-008
3-3
Planning Checklist
For the best fault tolerance, check that the 
uninterruptible power supplies are available to 
support the 6780 switches.
Task 5: Plan for the Power 
Requirements on page 3-13
Plan for the Hardware Hardware Installation and 
Migration Planning on page 3-5
Plan for the Nodes
If the servers are not already installed, check that 
the preinstallation planning for the servers and 
peripheral equipment is conducted in accordance 
with the required standards.
NonStop S-Series Planning and 
Configuration Guide
Check that no more than 96 servers are 
connected to a ServerNet cluster.
Task 1: Plan for the ServerNet 
Nodes on page 3-5
For each NonStop S-series server to join the 
ServerNet cluster, check that MSEBs are installed 
in slots 51 and 52 of the group 01 system 
enclosure.
Installing the Required 
Hardware in NonStop S-Series 
Servers on page 4-10
For the MSEBs in slots 51 and 52 of group 01 of 
each NonStop S-series server, check that the 
MSEBs contain a SMF PIC with the NNA FPGA in 
port 6.
Installing the Required 
Hardware in NonStop S-Series 
Servers on page 4-10
If MSEBs are to be installed in a NonStop S-series 
server, check that ServerNet cables with the 
appropriate connectors are available to connect 
the MSEBs to other system enclosures.
NonStop S-Series Planning and 
Configuration Guide
Plan for the System Consoles
Check that an adequate number of system 
consoles are available to manage the nodes in the 
cluster. 
Task 2: Plan for the System 
Consoles on page 3-6
Plan for the Switches
Check that the 6780 switches are either available 
or ordered. 
Task 3: Plan for the 6780 
Switches on page 3-8
Check that the PICs for each 6780 switch are 
either available or ordered.
Plan the PICs Needed for Each 
6780 Switch on page 3-10
Plan for the Racks
Check that enough 19-inch racks are available for 
the 6780 switches and other components. If you 
are providing your own racks, check that they 
meet the required specifications. 
Task 4: Plan for the Racks
 on 
page 3-12
Check that there is enough floor space to 
accommodate the footprint of each 19-inch rack.
Floor Space for the Racks
 on 
page 3-12.
Table 3-1. Planning Checklist  (page 2 of 3)
√ Major Planning Step For More Information