Note the following considerations for locating the cluster switches:
The power cord for a cluster switch and its power subsystem measures 8.2 feet
(2.5 meters).
A switch enclosure can be installed on the floor or on top of a base system
enclosure.
To reduce cabling errors, HP recommends that the X-fabric and Y-fabric cluster
switches be installed with some distance between them. Do not install the cluster
switches next to or on top of each other. See Figure 2-8.
Figure 2-8. Placement of Cluster Switches
ServerNet
Cluster Switch
(X Fabric)
ServerNet
Cluster Switch
(Y Fabric)
To avoid cabling errors, place the X-fabric and the Y-fabric switches in different locations
Do not stack
ServerNet Cluster
Switches on top of
each other.
Do not locate ServerNet
Cluster Switches next to
each other.
Do not stack ServerNet
Cluster switches on top of
a double-high stack.