ABORT TASK Command
ONLY
specifies that only the subordinate objects are affected.
Considerations
•
Existing activity over the WAN lines running in the CLIP is affected.
•
You must issue a START SERVER command before you can start new WAN lines
or download DLC tasks on the CLIP.
•
The state of the SERVER indicates whether the CLIP is being controlled by this
system.
•
After an ABORT SERVER command issued, the WANBoot process does not
respond to BOOTP requests from the CLIP.
•
After an ABORT SERVER command is issued, you can perform a firmware update
through the OSM Service Connection or TSM Service Application (G-series RVUs
only). For more information about using OSM or TSM, see the online help within
each application.
ABORT TASK Command
Use the ABORT TASK command to terminate the operation of the specified data link
control (DLC) task by placing the TASK object in the STOPPED state. The task is
removed from the CLIP RAM. Tasks previously copied to CLIP FLASH memory are not
affected.
The ABORT TASK command has this syntax:
conc-name.clip-num.dlc-task
indicates the task.
ABORT TASK $ZZWAN.#conc-name.clip-num.dlc-task
Value: The task name is the name of the task running on the SWAN
concentrator.
conc-name is the name of the SWAN concentrator as specified in
the ADD ADAPTER command.
clip-num is the CLIP number. The possible values for the CLIP
number are 1, 2, or 3 for a SWAN concentrator and 1, 2, 3, 4, 5, or
6 for a SWAN 2 concentrator.
dlc-task is the task running in a WAN port. The possible values
are DLC0 or DLC1. DLC0 indicates the task running in WAN port 0.
DLC1 indicates the task running in WAN port 1.
Default: None provided.