HP StorageWorks P9000 Cluster Extension Software Administrator Guide (TB534-96009, February 2011)
2. Update the settings as needed, and then click OK to close the window.
3. Click OK to save your changes and close the window.
Notes
• After a device/copy group is configured in the resource configuration utility, do not change
the device/copy group name or swap the name with another device/copy group name in
the HORCM file. If you do this, restart the HORCM manager instance and reconfigure the P9000
Cluster Extension resource.
• Do not use HORCM commands to change the device/copy group property for a device/copy
group that is configured for a P9000 Cluster Extension resource. If you do this, the changed
property is not reflected immediately in the Parameters tab. To work around this situation,
re-select the device/copy group from the P9000 device/copy group menu in the Parameters
tab.
Configuring server data center assignments
To configure server data center assignments from the Failover Cluster Management Parameters
tab or the resource configuration tool:
1. To remove a data center assignment, select the assignment, and then click Remove.
2. To modify a data center assignment, select the assignment, and then click Modify. Enter the
new Data center name in the Modify Node in Data Center List window, and then click OK.
3. To add a data center assignment, click Add. Select a host and a data center, and then click
OK.
4. Click OK to save your changes and close the window.
Changing failover and failback behavior
To configure failover and failback behavior from the Failover Cluster Management Parameters tab
or the resource configuration tool:
1. Click Failover/Failback to display the Failover/Failback window.
Configuring P9000 Cluster Extension resources 39