HP XP7 Site Preparation Guide (H6F56-96012)

Table 12 Floor load rating and required clearances for a three rack configuration (right module)
(continued)
Required Clearance (a+b) m
Clearance (c) m
Floor Load
Rating
(kg/m2)
C=1.4C=1.0C=0.8C=0.6C=0.4C=0.2C=0C=-0.3
Clearance (c) mRating
(kg/m2)
C=1.4C=1.0C=0.8C=0.6C=0.4C=0.2C=0C=-0.3
00000000Over 700
00000000.2600
00000.10.20.40.7500
000.10.20.40.50.71.1450
0.10.30.50.60.81.01.21.6400
0.50.81.01.11.31.61.82.3350
1.21.61.82.02.22.52.93.5300
Notes:
1. Actual clearances for installation should be determined after consulting with construction specialist responsible for
installation building, as they could vary depending on the size/layout of the system and building conditions.
2. When various configurations of disk arrays are arranged in a row, clearance values based on the largest disk
array configuration should be used.
3. From the viewpoint of maintenance operations, it is suggested that Clearance (c) be made as large as possible.
Four rack configuration (left module)
The following figure and table shows the service clearances and floor load rating for a four-rack
configuration (Setting up DKC rack in the left configuration).
24 Installation requirements