Figure 2 Service clearances for a two rack system (single DKC)
*1 Clearance (a+b) is based on the floor load rating and the clearance (c). Floor load rating and
required clearances are shown in Table 9 (page 17).
*2 Clearance (d) is required over 300mm to open the front door. In the case that the clearance
(d) is less tan the clearance (a), give priority to clearance (a).
Table 9 Floor load rating and required clearances for two rack configuration
Required Clearance (a+b) mFloor Load
Clearance (c) mRating
(kg/m2)
C=1.4C=1.0C=0.8C=0.6C=0.4C=0.2C=0C=-0.3
00000000Over 700
00000000.1600
Service clearance, floor cutout, and floor load rating 17