HP XP7 Site Preparation Guide (H6F56-96012)

Figure 4 Service clearances for a three rack system (left module)
*1 Clearance (a+b) is based on the floor load rating and the clearance (c). Floor load rating and
required clearances are shown in Table 11 (page 21).
*2 Clearance (d) is required over 300mm to open the front door. In the case that the clearance
(d) is less tan the clearance (a), give priority to clearance (a).
Table 11 Floor load rating and required clearances for a three rack configuration (left module)
Required Clearance (a+b) mFloor Load
Service clearance, floor cutout, and floor load rating 21