HP XP7 Site Preparation Guide (H6F56-96012)
Table 11 Floor load rating and required clearances for a three rack configuration (left module)
(continued)
Required Clearance (a+b) m
Clearance (c) m
Floor Load
Rating
(kg/m2)
C=1.4C=1.0C=0.8C=0.6C=0.4C=0.2C=0C=-0.3
Clearance (c) mRating
(kg/m2)
C=1.4C=1.0C=0.8C=0.6C=0.4C=0.2C=0C=-0.3
00000000Over 700
00000000600
000000.10.20.5500
0000.10.20.40.50.9450
00.20.30.40.60.81.01.3400
0.40.60.80.91.11.31.62.0350
1.01.31.51.72.02.22.63.1300
Notes:
1. Actual clearances for installation should be determined after consulting with construction specialist responsible for
installation building, as they could vary depending on the size/layout of the system and building conditions.
2. When various configurations of disk arrays are arranged in a row, clearance values based on the largest disk
array configuration should be used.
3. From the viewpoint of maintenance operations, it is suggested that Clearance (c) be made as large as possible.
Three rack configuration (right module)
The following figure and table shows the service clearances and floor load rating for a three-rack
configuration (Setting Up DKC-RACK in the Right Configuration).
22 Installation requirements