Hitachi Global Link Manager Software Installation and Configuration Guide

set to the port number that HiRDB uses. Therefore, reset the port
number.
¢
Please refer to next for the setting procedure of the cluster.
If the resources that registered version earlier than v8 is not in use by
other applications, you may want to delete this resources.
If Microsoft Failover Cluster is used:
Setting Up Microsoft Failover Cluster on page 4-9
5. Switch the group to which the services used by Global Link Manager have
been registered to the executing system.
Global Link Manager uses the following five services:
¢
HBase 64 Storage Mgmt Common Service
¢
HBase 64 Storage Mgmt SSO Service
¢
HBase 64 Storage Mgmt Web Service
¢
HBase 64 Storage Mgmt Web SSO Service
¢
HiRDB/ClusterService _HD1
If Microsoft Failover Cluster is used (on OSs other than Windows Server
2012):
In Failover Cluster Management, right-click the resource group to
which a Hitachi Command Suite product service has been registered,
and then select Move this service or application to another node.
If Microsoft Failover Cluster is used (on Windows Server 2012):
In Failover Cluster Manager, right-click the role to which the services
used by Global Link Manager have been registered, choose Move, and
then Select Node.
6. In Cluster Administrator, right-click the following services, select
Properties, select the Advanced tab, select Restart, and then click OK.
¢
HBase 64 Storage Mgmt Common Service
¢
HBase 64 Storage Mgmt SSO Service
¢
HBase 64 Storage Mgmt Web Service
¢
HBase 64 Storage Mgmt Web SSO Service
¢
HiRDB/ClusterService _HD1
If Microsoft Failover Cluster is used (on OSs other than Windows Server
2012):
In Failover Cluster Management, right-click the resource name, and
choose Properties, the Policies tab, then If resource fails.
Attempt restart on current node and If restart is unsuccessful,
fail over all resources in this service or application.
If Microsoft Failover Cluster is used (on Windows Server 2012):
Right-click the resource, and choose Properties, the Policies tab,
then If resource fails, attempt restart on current node and If
restart is unsuccessful, fail over all resources in this Role.
4-18
Installing Global Link Manager Clusters
Hitachi Global Link Manager Installation and Configuration Guide (Web Version)