HP Performance-Optimized Datacenter, 6 m (20 ft) User Guide

Installation 12
Installation
HP POD shipping contents
Component Quantity Part number
HP 50U rack 10 AT978A
Side panel 50U kit 1 AN991A
Rack interface seal kit 9 AP013A
One of the following busway dropboxes and PDU kit
3-phase HP POD PDU 20 AS614A (NA)
AS634A
(International)
3-phase HP POD busway dropbox kit 10 AS613A (NA)
AS633A
(International)
3-phase HP POD PDU bracket kit 20 AQ683A
The HP POD is delivered with heavy duty filler panels installed in every empty U space of the racks.
However, to prevent compromising the integrity of the cold aisle setpoint temperature when IT equipment
is removed for upgrade or maintenance, HP recommends purchasing additional HP POD Filler Panels
(AQ682A, AS993A).
The quantity and model of PDUs included with your HP POD are dependent on the IT equipment load they
are supporting.
Domestic 20-foot HP PODs are equipped with two built-in transformers. International 20-foot HP PODs do
not require a transformer or switchboard.
NOTE: The North American HP POD includes step-down isolation transformers and requires
two 400A, 480V, 3-phase delta feeds at 50-60 Hz.
Preinstallation checklist
All components have been delivered to your facility.
The HP POD is its final location.
Tighten the electrical busway interconnects before you begin the installation process.
You have facility power at your final location. You can provide the connection cables from the
facility to the HP POD or purchase connection cables from HP at an additional cost.
You have facility water at your final location. You can provide the connection hoses from the facility
to the HP POD or purchase connection hoses from HP at an additional cost.
You have properly grounded the HP POD.