HP Performance-Optimized Datacenter, 6 m (20 ft) User Guide

Installation 18
Verify accurate electrical installation.
Verify accurate mechanical installation.
Test the operation of the ECS and Cooling controls.
Test the operation of the smoke detection system.
Test the operation of EPO system.
Test the operation of the analog and digital phone system (optional).
Verify initial IT start-up.
Conduct an infrared scan of all electrical connections under the start-up IT load.
Verify accurate cooling under start-up IT load.
Provide the HP POD operation owner training.