HP Performance Optimized Datacenter 20c Site Preparation and Requirements Guide - China Abstract This document provides site preparation guidance and site requirements for the HP Performance Optimized Datacenter 20c (HP POD 20c).
© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. The only warranties for HP products and services are set forth in the express warranty statements accompanying such products and services. Nothing herein should be construed as constituting an additional warranty. HP shall not be liable for technical or editorial errors or omissions contained herein.
Contents Overview ..................................................................................................................................... 5 About this document .................................................................................................................................. 5 Safety information ..................................................................................................................................... 5 Site assessment ..................................
HP Site Preparation Drawing Package ....................................................................................................... 22 Zoning and permit requirements ................................................................................................................ 22 Project coordination................................................................................................................................. 22 Site planning .......................................................
Overview About this document This document outlines the site and preparation requirements for a 6 m (20 ft) HP POD 20c as it is being released in China. The customer must provide a qualified architectural or consulting engineering team to generate site-specific documents for each HP POD 20c installation, including final site drawings. The customer site installation design must comply with all national, regional, and local regulations, ordinances, codes, and the specifications listed in this document.
The HP standard suppression system includes an FM200 clean agent system. However, if the customer or local AHJ requires specific modifications or a replacement, HP can assist in these actions at the expense of the customer. HP does not certify that the fire suppression system installed in the HP POD 20c meets all local and jurisdictional requirements.
HP POD 20c capacities HP POD 20c capacity limitations The capacity limitations for the HP POD 20c are separated into two categories: electrical power and mechanical cooling capacities. Both of these categories are interdependent and must be considered in conjunction with the overall customer requirements. Electrical power capacities (critical IT power) The electrical system of the HP POD 20c contains two main feeds, A and B, that are each rated at 400 A 380-415 VAC Wye 3-Phase.
Site requirements Site pad The structural design of the HP POD 20c site pad must be based on the specific weight load of the complete POD solution with IT installed, as well as any additional equipment. During design calculations, HP recommends that you provide structural support along the entire perimeter of the POD and use the maximum allowable POD weight. Upon installation, the POD structure must be leveled to ≤ 0.5º.
End 1 view clearances shown Top view keep-out and door swing clearances shown (shaded areas indicate the required clearance) Site requirements 9
Top view clearances shown Side view for multiple POD installation minimum clearances shown Adequate space around the HP POD 20c is necessary for minimum door clearance. These minimum clearances provide room for door opening only. Consider additional space as necessary for your site. Safety and clearance area WARNING: Check for electrical distribution and transmission lines in, over, and under the construction site and maintain a safe working clearance from energized electrical lines.
• • • Working distance clearance—Maintain a safe working clearance according to the local utility company or AHJ for each of the following items: o Buildings o Fences o Gate headers o Underground and overhead utilities Infrastructure clearance o Underground power conduits, excluding power, water, and drainage lines connected to the HP POD 20c o Underground water lines, excluding power, water, and drainage lines connected to the HP POD 20c o Underground sewage lines, excluding power, water, a
Grounding feature Specification Grounding lugs • • Ground rod system or ground well The customer must provide an effective grounding system with a ground rod or a ground well. Grounding lugs cannot be attached to any painted surface. Grounding lugs must be compression-type 2-hole lugs and UL listed specifically for grounding. IMPORTANT: Before installing the HP POD 20c, consult your local AHJ for applicable codes and to review site-specific location guidelines.
Requirement Specification Organic compounds None Type of water Drinking water. Do not use de-mineralized or softened water. Instant water fill flow rate 0.6 lpm (0.16 gpm) Humidifier For the exact requirements, see the humidifier documentation. IMPORTANT: If your water is out of range, consult a water quality expert. IMPORTANT: You must provide a humidification water supply isolation valve that is external to the HP POD 20c.
IMPORTANT: Operating the chilled water system at the higher end of the acceptable range decreases the overall thermal capacity of the POD. Acceptable water quality specifications Water must be maintained per the following acceptable water quality standards. Parameter Range pH 8.
• PVC IMPORTANT: Even though some PVC grade piping materials are designed to handle the expected water pressure, the use of PVC materials should be reviewed and approved by the customer site engineers.
IMPORTANT: All 3-Phase Wye feeders for the HP POD 20c require that the neutrals and the equipment grounding conductors remain isolated. Bonding of the two conductors is allowed at the power source only.
Supported facility connections Environmental control system The ECS developed for the HP water-cooled POD is a stand-alone control system that requires no external connections with an external site system, BMS, public or private Internet sites, cloud, or wireless system to properly control the POD operation. The ECS includes Modbus TCP/IP connections through which a variety of data can be retrieved.
End view shown Fire box The communication connections between the fire system and the HP POD 20c are made through the fire box. End view shown You must make the connections between the facility and the HP POD 20c. For configuration and installation instructions, consult with HP.
• ECS communication • Security communication • Telephone End view shown You must make the connections between the facility and the HP POD 20c. For configuration and installation instructions, consult with HP. Humidifier A dedicated water supply and approved drainage is required for the humidifier. For more information about the humidifier, see the HP Performance Optimized Datacenter 20c User Guide provided with the HP POD 20c.
IMPORTANT: Confirm with the AHJ that condensate water and rain water can be mixed in the same drainage. HP POD 20c security The HP POD 20c is equipped with standard key lock hardware for each personnel entry door and external electrical cabinet. Each personnel entry door includes a door access contact that can be connected to the customer facility security system.
Environmental considerations Environmental risks • Avoid placing the HP POD 20c directly along a drainage path or in an area prone to flooding. • Verify that the HP POD 20c is properly grounded in accordance with national, regional, and local regulations, ordinances, codes, and the product specifications. Cold weather The HP POD 20c requires a site chilled water supply and return, humidifier supply and drain, and condensate drains. Extreme cold weather can cause damage to the supply and drain lines.
Site plan requirements and actions Completing a site assessment HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP POD 20c. Consult with HP to schedule a site assessment.
• Ensure that the site safety and security programs are properly administered. • Interface directly with the HP installation project manager to ensure clear lines of communication during the installation and commissioning processes. Site planning A comprehensive site plan assists with the site design (MEP) and ensures the best possible HP POD 20c installation process.
• Assembly equipment locations HP POD 20c lifting requirements WARNING: The only approved method for lifting the HP POD 20c is the use of a spreader bar harness. Lifting an HP POD 20c in any other manner can cause damage to the HP POD 20c and void your warranty. HP POD 20c storage requirements If the site is not ready for assembly and operation, determine a location for storage when creating the site plan.
• Access landings might be required to maintain the required access to the HP POD 20c electrical panels.
Appendix A: HP site assessment HP POD 20c site assessment checklist During a survey of the readiness of a proposed customer site for the HP POD 20c, the site is inspected for the following: • Accessibility of machinery for the transportation and installation of the HP POD 20c • Assessment of the suitability of the site infrastructure for installing the HP POD 20c and for supporting infrastructure preparation and serviceability requirements HP responsibilities Item Description Sign-off 1.
Item Description Sign-off Inspect the proposed installation site to confirm clearance requirements for installation and serviceability as per the HP POD 20c specifications. Necessary clearances are determined, in part, based on the specific installation plans and infrastructure design. Location, orientation, and planned utilization can affect the necessary clearances. Consider future planning for the space around the installation site. Evaluate the HP POD 20c installation site in relation to 9.
Item Description 14. Security Conduct interviews with the customer site engineering personnel to determine the level of security required for the HP POD 20c and its infrastructure. The proposed installation site is assessed for suitability in relation to the customer requirements. Following the HP installation site visit, analyze the data collected and prepare a report of findings.
Item Description Sign-off Arrange site-specific project logistics at the time of scheduling. Failure to provide necessary authorizations can limit the effectiveness of the service and can, at the discretion of HP, impact scheduling or result in the postponement of the service. 11. Business visas Provide assistance in instances where a temporary business visa is required for HP personnel to visit the site. This assistance typically takes the form of preparing a letter of invitation.
Appendix B: Preparing for delivery Pre-delivery tasks Allow adequate time for planning, scheduling, obtaining permits, design approval, inspections, and so on. Installation prerequisites Before installing the HP POD 20c, verify that the following prerequisites are met: • All components are delivered to the facility. • The HP POD 20c and power distribution components are in the final location. • Facility power, water, and drainage are at the final location.
Item Description 7 When installing on an elevated surface, verify that the maximum height requirements for the circuit breaker actuator meet the national, regional, and local regulations. Verify that proper landings and the catwalk are planned for electrical cabinet access. Verify the planning for required egress routes for all HP POD 20c personnel doors, cargo doors, and service area doors, including landings, the catwalk, and stairs.
Item Description 29 Verify the location of the remote electronic monitoring system. 30 Verify that tie-downs and other AHJ-required facilities for the HP POD 20c and power containers are complete at least one week prior to arrival of HP-provided equipment. Sign-off General water supply Item Description 1 Verify that the site drainage is complete, and the HP POD 20c is not in a drainage path or flood prone area.
Glossary AHJ authority having jurisdiction BMS building management system door A hinged portion of an enclosure that covers an opening. ECS environmental control system EPO emergency power off equipment A general term, including fittings, devices, appliances, luminaires, apparatus, machinery, and the like used as a part of, or in connection with, a modular data center. (Source: NEC.
UPS uninterruptible power system VESDA very early smoke detection apparatus Glossary 34
Documentation feedback HP is committed to providing documentation that meets your needs. To help us improve the documentation, send any errors, suggestions, or comments to Documentation Feedback (mailto:docsfeedback@hp.com). Include the document title and part number, version number, or the URL when submitting your feedback.
Index A humidifier 19 I about this guide 5 areas prone to lightning or power surges 21 assembly 30 assembly area 23 installation 23 installation equipment 23 IT cable portals 17 C L central facility infrastructure connections 17 clearance area 8, 10 cold weather considerations 21 connection portals 17 connections, additional 17 connections, facility 17 lifting layout and requirements 23 lightning protection 21 D delivery considerations 30 dimensions 8 drainage 13 E electrical power capacity 7 elec
site planning considerations 23 site preparation 5 site preparation checklist 30 site requirements 8 storage locations 24 supported facility connections 17 system capacity 7 U utilities 12 V vestibule specifications 24 W water supply 12, 13 weight 8 Z zoning and permit requirements 22 Index 37